1
MH/ KNT Border Sangareddy
Karnataka
BOT |
9 |
145 |
|
|
L&T Infrasructure Developement Projects Ltd-
Indian- |
|
- - |
2
Hospet - Chitradurga
Karnataka
BOT |
13 |
120.03 |
|
|
Ramkey Infrasructure Ltd-
Indian- |
|
- - |
3
4-Laning of Cuttak - Angul
Orissa
BOT |
42 |
112 |
|
|
Ashoka Buildcon-
Indian- |
|
- - |
4
Rampur - Kathgodam
Uttaranchal
BOT |
87 |
93.226 |
|
|
ERA Infra Engineering Ltd.-OJSC-SIBMOST (JV)-
Indian - Russian- |
|
- - |
5
4 Laning of Brahampore-Faraka Km 191.416 to Km 294.684 West Bengal
BOT |
34 |
103 |
Feb 2011
|
Aug 2013
|
Hindustan Construction Company Ltd.-
Indian- |
Aug 2013
|
URS Scott Wilson Indian Pvt. Ltd. In Associate with Rodic Consultant P Ltd.- Indian - |
6
4 Laning of Faraka-Raiganj Km 295.00 to Km 398.00 West Bengal
BOT |
34 |
103 |
Feb 2011
|
Aug 2013
|
Hindustan Construction Company Ltd.-
Indian- |
Aug 2013
|
URS Scott Wilson Indian Pvt. Ltd. In Associate with Rodic Consultant P Ltd.- Indian - |
7
4 Laning of Raiganj-Dalkola Km 398.00 to Km 452.75 West Bengal
BOT |
34 |
50 |
Feb 2011
|
Aug 2013
|
Hindustan Construction Company Ltd.-
Indian- |
Aug 2013
|
URS Scott Wilson Indian Pvt. Ltd. In Associate with Rodic Consultant P Ltd.- Indian - |
8
4-Laning of Rohtak-Jind (Approved Length 45 Km)
Haryana
BOT |
71 |
48.6 |
|
|
Vijai Infrastructure Ltd.-
Indian- |
|
- - |
9
4 Laning of UP/Haryana Border-Yamunanagar-Saha-Barwala- Panchkula Km 71.64 to Km 179.249 Haryana
BOT |
73 |
107 |
|
|
Gammon Infrastructure Projects Ltd.-
Indian- |
|
- - |
10
4-Laning of Solapur - Maharashtra/ Karnatka Section Km 249.00 to Km 348.80 Maharashtra
BOT |
9 |
100.06 |
|
|
Coastal-SREI Consortium-
Indian- |
|
Artefact Projects Ltd.- Indian - |
11
4 Laning of Solapur - Bijapur Km . 0.00 to Km. 110.542 Maharashtra[35]/Karnataka[75.542]
BOT |
13 |
110.542 |
|
|
Sadbhav Engineering Limited-
Indian- |
|
- - |
12
Four lanning of Ludhiyana- Talwandi section km. 92.00 to km. 170.00 Punjab
BOT |
95 |
78 |
Mar 2012
|
Sep 2014
|
Essel Infra Projects Ltd.- Pan Indian Networks Ltd.-
Indian- |
Sep 2014
|
Louis Berger Group, Inc in Asso. With LBC Pvt. Ltd.- USA - |
13
Bhopal-Sanchi(Approved Length 40 Km)
Madhya Pradesh
Annuity |
86Ex |
53.78 |
Oct 2011
|
Jan 2013
|
Pratibha Industries-Abhyuday Housing Construction Ltd-
Indian- |
Oct 2013
|
Consulting Engg. Services (I) Pvt. Ltd.- Indian - |
14
Ghaziabad-Aligarh (Approved Length 106 )
Uttar Pradesh
BOT |
91 |
126 |
Feb 2011
|
Aug 2013
|
SREI - PNC - GALFAR Consortium-
Indian - Dubai- |
Aug 2013
|
SNC-Lavalin Infrastructure Pvt. Ltd.- Canada - |
15
4/6 Laning of Maharastra/Goa Border - Panaji Goa/KNT Border
Goa
BOT |
17 |
139 |
|
|
IVRCL Infrastructure & Projects Ltd-
Indian- |
|
- - |
16
4-lanning of Kannur Vengalem Kuttipuram (Package -I) Km 148 to km 230 Kerala
BOT |
17 |
83.2 |
|
|
KMC Construction Ltd.-
Indian- |
|
- - |
17
KNT/Kerala Border to Kanuur Section(Approved Length 286.3)
Kerala
BOT |
17 |
126.6 |
|
|
Transstry-OJSC Consortium-
Indian-Russian- |
|
CDM Smith in Jv With Wilbur Smith Associates- Indian-USA - |
18
4-lanning of Kannur Vengalem Kuttipuram (Package -II) Km 230 to km 318 Kerala
BOT |
17 |
81.5 |
|
|
KMC Construction Ltd.-
Indian- |
|
- - |
19
Panji-Goa/Karnatka Border
Goa
BOT |
4A |
69 |
|
|
IRB-MRM Consortium-
Indian- |
|
- - |
20
4 Laning of Barhi - Hazaribagh(Approved Length 40 Km)
Jharkhand
BOT |
33 |
41.314 |
Feb 2012
|
Feb 2014
|
Abhijeet Infrastructure Ltd-Corporate Ispat Alloy Ltd(JV)-
Indian- |
Feb 2014
|
SAI- Indian - |
21
Ranchi - Rargaon - Jamshedpur Km 114.00 to Km 277.50 Jharkhand
Annuity |
33 |
163.5 |
Dec 2012
|
Jun 2015
|
Madhucon Projects Ltd.-
Indian- |
Jun 2015
|
Aarvee- Indian - |
22
4-Laning of Punjab/Haryana Border-Jind Km. 239.00 to Km 307.00 Haryana
BOT |
71 |
68 |
|
|
Unity Infraprojects Ltd.-
Indian- |
|
- - |
23
2 Laning of Jowai -Meghalaya/Assam Border (Approved length 109 Km) Km. 69.20 to Km. 173.20 Meghalaya
BOT |
44 |
102 |
|
|
Simplex Infrastructure Ltd.-
Indian- |
|
- - |
24
4 Laning of Khagaria-Bakhtiarpur Km. 0.00 to Km 112.982 (existing chainage from Km. 153.30 to Km. 270.00) Bihar
BOT |
31 |
112.982 |
|
|
Navayuga Engineering Company Ltd.-
Indian- |
|
- - |
25
2-Laning with PS khagaria - Purnea
Bihar
Annuity |
31 |
140 |
May 2011
|
Feb 2014
|
Punj Lloyd Infrastructure Ltd.-
Indian- |
Apr 2014
|
Bloom Infrastructure- USA - |
26
2-Laning with PS Motihari-Raxaul (Approved Length 67 Km)
Bihar
BOT |
28A |
68.79 |
Oct 2011
|
Apr 2014
|
Tantia-Jiangsu (JV)-
Indian-China (JV)- |
Apr 2014
|
Frischmann Prabhu (India) Pvt. Ltd.- Indian - |
27
2 Laning of Forbesganj-Jogwani(Approved Length 13 Km)
Bihar
Annuity |
57A |
9.258 |
Mar 2011
|
Oct 2013
|
GPT-RDS Consortium Ltd-
Indian- |
Oct 2013
|
Unihorn India Pvt. Ltd.- Indian - |
28
2-Laning with PS Gopalganj-Chappra Km 0.00 to Km 94.7 Bihar
Annuity |
85 |
92 |
Dec 2011
|
May 2014
|
Abhijeet Infrastructure Ltd.-
Indian- |
May 2014
|
CEG- Indian - |
29
4 Laning of Chappra-Hajipur(Approved Length 153 Km)
Bihar
Annuity |
19 |
65 |
Jan 2011
|
Jul 2013
|
Madhucon Projects Ltd-
Indian- |
Jul 2013
|
Stanly Cunsultant Inc- USA - |
30
Patna - Buxar
Bihar
BOT |
30 & 84 |
124.85 |
|
|
Gammon Infrastructure Projects Ltd-
Indian- |
|
Bloom Infrastructure- USA - |
31
2 Laning of Muzaffarpur - Sonbarsa(Approved Length 89 Km)
Bihar
Annuity |
77 |
86 |
May 2011
|
Nov 2013
|
BSCPL-C&C(JV)-
Indian- |
Nov 2013
|
ICT Pvt Ltd.- Indian - |
32
2 Laning of Mokama-Munger(Approved Length 70 Km)
Bihar
Annuity |
80 |
69.27 |
May 2011
|
May 2013
|
BSCPL -C & C Consortium-
Indian- |
Mar 2014
|
Nicholoso'-Dwyer-Upham Infrastructure- Irland-Indian(JV) - |
33
Indore-Jhabua-Gujrat/MP (Approved Length 168)
Madhya Pradesh
BOT |
59 |
155.15 |
Oct 2010
|
Apr 2013
|
IVRCL Infrastructure Projects Ltd.-
Indian- |
Apr 2013
|
EURO Studios Feedback Venture- - |
34
4 Laning of Mulbagal - Karnataka / AP border-Approved Length (11 Km) Km .216.912 to Km.239.10 Karnataka
BOT |
4 |
22.18 |
|
|
J.S.R. Construction Pvt Ltd-
Indian- |
|
- - |
35
Sambalpur-Baragarh-Chattisgarh/Orrisa Border Km 0.00 to Km 88 Orissa
BOT |
6 |
88 |
Nov 2011
|
May 2014
|
Ashoka Buildcon Ltd-(Ashoka Sambalpur Baragarh Expressway Pvt. Ltd.)-
Indian- |
May 2014
|
ICT- Indian - |
36
Talegaon-Amravat(Approved Length 58Km)
Maharashtra
BOT |
6 |
67.8 |
Nov 2009
|
Nov 2013
|
IRB-MRM Consortium-
Indian- |
Nov 2013
|
Wilbur Smith Associates Pvt. Ltd.- Indian - |
37
Gujarat/Maharashtra Border-Surat - Hazira Port Section Km. 0.0 to Km. 132.913 Gujarat
BOT |
6 |
132.9 |
Mar 2010
|
Sep 2012
|
Isolux-Soma Consortium (JV)-
Spain-Indian- |
Dec 2013
|
Sheladia Association Inc.-Multimedia Consultant Pvt Ltd- USA-Indian - |
38
Kishangarh-Ajmer-Beawar
Rajasthan
BOT |
8 |
93.56 |
Nov 2009
|
May 2012
|
Isolux-Soma Consortium-
Spain-Indian- |
Jun 2013
|
Louis Barger Group, Inc USA- USA - |
39
4 laning of Jetpur-Somnath section of NH-8D (approved length 127.6) km 0 to km 127.6 Gujarat
BOT |
8D |
123.45 |
Mar 2012
|
Sep 2014
|
IDFC-PLUS Expessway Berhad Consortium-
Indian-Malaysian (JV)- |
Sep 2014
|
- - |
40
Pune-Sholapur Pkg-I(Approved Length Pkg I & II 170 Km)
Maharashtra
BOT |
9 |
110.05 |
Nov 2009
|
Mar 2012
|
Navinya Buildcon-Atlantia Spa(JV)-
Indian-Italy- |
Oct 2013
|
Renardet S.A.- Switzerland - |
41
Pune-Sholapur Pkg-II(Approved Length I & II 170 Km)
Maharashtra
BOT |
9 |
105 |
Sep 2011
|
Jan 2014
|
IL & FS Transportation Network Ltd-
Indian- |
Jan 2014
|
ICT Pvt. Ltd.- Indian - |
42
4-Laning of Rohtak - Hissar Section Km87.0 to Km170.0 includ. conn. Link from Km87.0(NH-10) to Km348.0(NH-71) Haryana
BOT |
10 |
98.81 |
|
|
Sadbhav Engg. Limited-
Indian- |
|
- - |
43
Beawar-Pali-Pindwara (Approved Length - 246 Km)
Rajasthan
BOT |
14 |
244.12 |
Dec 2011
|
Jun 2014
|
L&T Infrastructure Development Projects Ltd.-
Indian- |
Jun 2014
|
Sheladia-Aarvee- USA-Indian - |
44
Panvel-Indapur
Maharashtra
BOT |
17 |
84 |
Dec 2011
|
Jun 2014
|
Supreme Infrastructure India Ltd.-Mahavir Road & Infrastructure Pvt. Ltd.-China State Construction Engg. Hongkong Ltd.-
Indian-China- |
Jun 2014
|
Yongma Engg.Co.Ltd. In Asso. With Feedback Venture Pvt. Ltd.- Korea-Indian - |
45
Kudapa-Mydukur-Kurnool Km 167.750 to 356.502 Andhra Pradesh
BOT |
18 |
188.752 |
Nov 2010
|
May 2013
|
KMC Construction Ltd. - IVRCL Consortium-
Indian- |
Sep 2013
|
Aarevee Associates Architects- Indian - |
46
Muradabad-Bareily (Approved Length 112)
Uttar Pradesh
BOT |
24 |
121 |
Apr 2010
|
Jun 2013
|
IL & FS Transportation Ltd.-
Indian- |
Jun 2013
|
LBG- USA - |
47
Bareily - Sitapur(Approved Length 134 Km) Km 262 to Km 413.200 Uttar Pradesh
BOT |
24 |
151.2 |
Mar 2011
|
Sep 2013
|
ERA-SIBMOST-
Indian-Russian- |
Sep 2013
|
Intercontinental Consultant Pvt. Ltd.- Indian - |
48
2 Laning of Dindigul-Perigulam-Theni-Kumili
Tamil Nadu
Annuity |
220 |
134 |
Sep 2011
|
Aug 2013
|
Transstroy-OJSC Consortium Ltd-
Indian-Russian- |
Aug 2013
|
ICT Private Limited- Indian - |
49
4 Laning of Ahmedabad to Godhara (Approved Length 210 Km)
Gujarat
BOT |
59 |
117.6 |
Dec 2010
|
Jun 2013
|
ESSEL Infra & CR-18 Consortium-
Indian-china- |
Jun 2013
|
Egis International-Egis India Consulting Engg. Pvt. Ltd.- France-Indian - |
50
4 Laning of Godhara to Gujarat /MP Border(Approved Length 210 Km)
Gujarat
BOT |
59 |
87.285 |
Mar 2011
|
Aug 2013
|
BSPCL Ltd-
Indian- |
Aug 2013
|
Intercontinental Consultants and Technocrats Pvt. Ltd.- Indian - |
51
4 Laning of Coimbatore-Mettupalayam Km 323/850 to Km 377/780 Tamil Nadu
BOT |
67 |
53.93 |
|
|
Transstroy-OJSC Consortium-
Indian- |
|
- - |
52
Four Laning of Kiratpur-Ner Chowk Section Km. 73.20 to Km. 186.50 Himanchal Pradesh
BOT |
21 |
84.32 |
|
|
IL & FS Transportation Networks Ltd.-
Indian- |
|
Getinsa Ingenieria S.L.Spain in Asso. with Segmental Cons. & Supp. Pvt. Ltd- Spain-Indian - |
53
4 Laning of Obedullaganj-Betul Section Km. 2.80 to Km 8.30 Madhya Pradesh
BOT |
69 |
125 |
|
|
Transstroy (India) Ltd.-
Indian- |
|
- - |
54
Patna- Muzzaffarpur
Bihar
Annuity |
19 & 77 |
63 |
Aug 2010
|
Feb 2013
|
Gammon Infrastructure Ltd-
Indian- |
Oct 2013
|
ICT- Indian - |
55
Muzaffarnagar - Haridwar (Approved Length 77 )
Uttar Pradesh[21]/Uttaranchal[59]
BOT |
58, 72 |
80 |
Sep 2011
|
Mar 2013
|
ERA-SIBMOST-
Indian - Russian- |
Mar 2014
|
Nicholas O'Dwyer and SA Infra- - |
56
Haridwar - Dehradun (Approved Length 69)
Uttaranchal
Annuity |
72 |
39 |
Nov 2011
|
Oct 2013
|
ERA - SIBMOST(JV)-
Indian - Russian- |
Mar 2014
|
Intercontinental Consultants & Technocrats Pvt. Ltd.(ICT)- Indian - |
57
Bhubneshwar-Puri(Approved Length 59 Km) Km 0.00 to Km 59 Orissa
BOT |
203 |
67 |
Mar 2011
|
Aug 2013
|
KSS-Valecha (Bhubneshwar Expressway Pvt. Ltd.)-
Indian- |
Aug 2013
|
CEG Ltd.- Indian - |
58
Tirupati -Tiruthani - Chennai(Approved Length 125.5 Km) Km 274.800 - Km 341.6 to Km 0.00 to Km 59.6 Tamil Nadu[61.47]/Andhra Pradesh[63.23]
BOT |
205 |
124.7 |
Apr 2011
|
Oct 2013
|
Transstroy -OJSC Consortium(JV)-
Indian-Russian- |
Oct 2013
|
Wilbur Smit Associates in Jv with Wilbur Smit Associates Pvt. Ltd.- USA-Indian - |
59
Panikholi-Rimoli (Approved Length 106 Km) Km 0.00 to Km 163.00 Orissa
BOT |
215 |
163 |
|
|
Gayatri Projects Ltd.-
Indian- |
|
Aarvee Associates Pvt. Ltd.- Indian - |
60
Trichy - Karur
Tamil Nadu
BOT |
67 |
79.7 |
Jan 2008
|
Jul 2010
|
Reliance Energy Limited-
Indian- |
Sep 2013
|
WSA Wilbar Smith Associates- USA - |
61
Panipat - Rohtak(Approved Length 73 Km)
Haryana
BOT |
71A |
80.858 |
Apr 2011
|
Oct 2014
|
Sadbhav Engineering Ltd-
Indian- |
Oct 2014
|
- - |
62
Rohtak - Bawal(Approved Length 97 Km)
Haryana
BOT |
71 |
82.553 |
May 2011
|
Nov 2013
|
JMC-SREI(JV)-
Indian- |
Nov 2013
|
- - |
63
Hazaribagh-Ranchi
Jharkhand
Annuity |
33 |
75 |
Aug 2010
|
Jan 2013
|
ITNL-Punj Lloyd Ltd.(JV)
(Hazaribagh Ranchi Express way ltd)-
Indian- |
Jun 2013
|
Unihorn India Pvt.Ltd- Indian - |
64
Barasat - Krishnanagar Km. 31.00 to Km.115.00 West Bengal
Annuity |
34 |
84 |
Aug 2012
|
Feb 2015
|
Madhucon Projects Ltd.-
Indian- |
Feb 2015
|
LEA Associates South Asia Pvt. Ltd.- Indian - |
65
Krishnanagar - Berhampore Km. 115.00 to Km.193.00 West Bengal
Annuity |
34 |
78 |
Feb 2012
|
Jul 2014
|
SEW Infra.-
Indian- |
Jul 2014
|
YJ Eng. Company Limited in Asso. with Feedback Infra. Services. Pvt. Ltd.- Indian - |
66
Amritsar - Pathankot (Approved Length 101Km) Km 6.082 to 108.502/102.4 Km Punjab
BOT |
15 |
106 |
May 2010
|
Nov 2012
|
IRB-MRM Pvt Ltd.-
Indian- |
Jun 2013
|
ICT in asso. With MC Consulting Eng. & Singhania & Partners- Indian - |
67
Patna - Bakhtiarpur km. 181.3 to km. 231.95 Bihar
BOT |
30 |
50.6 |
Sep 2011
|
Mar 2014
|
BSC-C & C (JV)-
Indian- |
Mar 2014
|
CEG- Indian - |
68
4 Laning of Belgaum-Khanpur Section(Km 0.00 to Km 30.00) and 2 Laning with paved sholuders of khanpur-Knt/Goa border.(Km 30.00 to Km 84.120)
Karnataka
BOT |
4A |
81.89 |
Mar 2011
|
Sep 2013
|
GVR Infra Projects-RMN Infrastructure Ltd-
Indian- |
Jul 2014
|
Lea Associates South Asia Ltd.- Indian - |
69
Pimpalgaon - Nasik - Gonde
Maharashtra
BOT |
3 |
60 |
Jan 2010
|
Jul 2012
|
Larsen & Toubro Ltd. - ABL Consortium-
Indian- |
Jun 2013
|
Sheldia-Theme- USA-Indian - |
70
Hungund-Hospet (Approved Length 194 Km)
Karnataka
BOT |
13 |
97.89 |
Sep 2010
|
Mar 2013
|
GMR-OSE Consortium-
Indian- |
Jun 2013
|
SMEC- Indian - |
71
Nagpur-Wainganga Bridge (Approved Length - 60 Km)
Maharashtra
BOT |
6 |
45.43 |
Apr 2012
|
Oct 2014
|
JMC Projects India Ltd.-
Indian- |
Oct 2014
|
Artefact Projects Ltd.- Indian - |
72
Nagpur - kondhali Km 9.2 to Km 50 Maharashtra
BOT |
6 |
40 |
Jun 2006
|
Dec 2008
|
Atlanta - SREI Consortium (JV)-
Indian- |
Jun 2013
|
Aarvee Associates- Indian - |
73
Vijayawada-Machhlipatnam km 0.0 to 63.8 Andhra Pradesh
BOT |
9 |
64.611 |
|
|
Madhucon Projects Ltd.-
Indian- |
|
- - |
74
Delhi/Haryana Border to Rohtak
Haryana
BOT |
10 |
63.49 |
May 2008
|
May 2010
|
KCT - ERA consortium-
Indian- |
Jun 2013
|
ICT Pvt Ltd- Indian - |
75
Reengus - Sikar Km. 298.075 to Km 341.962 Rajasthan
Annuity |
11 |
43.887 |
Mar 2012
|
Sep 2014
|
G.R.Infraprojects Ltd.-
Indian- |
Sep 2014
|
- - |
76
Jaipur-Reengus(Approved Length 52.65 Km )
Rajasthan
BOT |
11 |
54 |
Aug 2010
|
Feb 2013
|
RIL-AAA- JTEG Consortium-
Indian-China- |
Jul 2013
|
M/S Grontmij Carl Bro (Denmark) in JV with SAI Consulting Engineers Pvt. Lt- Denmark-Indian - |
77
Kota - Jhalawar
Rajasthan
BOT |
12 |
88.09 |
|
|
Keti Constructions Ltd.-
Indian- |
|
Sai Consulting- Indian - |
78
Deoli - Kota
Rajasthan
BOT |
12 |
83 |
Jan 2011
|
Jul 2013
|
GVK Development Projects Pvt Ltd-
Indian- |
Jul 2013
|
Scott Wilson Ltd-Scott Wilson India(JV)- UK-Indian - |
79
Jaipur-Tonk - Deoli(Approved Length 148.77 Km )
Rajasthan
BOT |
12 |
150 |
Jun 2010
|
Dec 2012
|
IRB-MRM Consortium-
Indian- |
Apr 2013
|
M/S Aarvee Associates Architects, Engineers & Constt. Pvt. Ltd- Indian - |
80
Kundapur-Surathkal & Mangalore-KNT/Kerala Border
Karnataka
BOT |
17 |
90 |
Sep 2010
|
Mar 2013
|
Navayuga - KPCL Consortium-
Indian- |
Jun 2014
|
Aarvee Associates Architect Engineers and Consultants Pvt. Ltd.- Indian - |
81
Aurang - Raipur Km 232 to Km. 281 Chattisgarh
BOT |
6 |
43.485 |
Apr 2006
|
Jan 2009
|
Apollo(UK) - JLI(UK) - DSC(Indian) - LOR(UK) Consortium-
UK - Indian JV- |
Dec 2013
|
Renardet S.A - Feedback Turnkey Engineers- Switzerland-Indian - |
82
Rimoli - Roxy - Rajamunda(Approved Length 163Km) 163 to 269 Km Orissa
BOT |
215 |
96 |
Jul 2011
|
Jan 2014
|
MBL-SREI-
Indian- |
Jan 2014
|
Lea Associates Pvt. Ltd.- Indian - |
83
Charthalai-ochira
Kerala
BOT |
47 |
83.6 |
|
|
ISOLUX-SOMA-
Spain-Indian- |
|
- - |
84
Devihalli-Hassan(Approved Length 73 Km)
Karnataka
BOT |
48 |
77.23 |
Dec 2010
|
May 2013
|
Larsen & Toubro Ltd.-
Indian- |
Jun 2013
|
Lea Associates South Asia Pvt . Ltd.- Indian - |
85
2-Laning of Krishnagiri-Tindivanam (Approved Length 170 Km.) Km. 37.6 to Km. 214.11 Tamil Nadu
Annuity |
66 |
176.51 |
Apr 2012
|
Apr 2014
|
Transstroy (I) Ltd. - Corporation Transstroy OJSC Consortium-
Indian - Russian- |
Apr 2014
|
- - |
86
Two Laning of Trichy - Karaikudi and Trichy Bypass(Approved Length 100 Km) KM 10.00 to Km 94.00 & Km 110.016 to Km 135.930 Tamil Nadu
Annuity |
210 & 67 |
110.372 |
May 2011
|
May 2013
|
Transstroy Ltd-OJSC Consortium-
Indian-Russian- |
May 2013
|
Euroestudios, S.L. Spain In associated with Theme Engg. Services Pvt.Ltd.- Spain-Indian - |
87
Thanjarur - Trichy km 80 - km 135.750 Tamil Nadu
BOT |
67 |
56 |
Dec 2006
|
Jun 2009
|
Madhucon Projects Ltd.-
Indian- |
Apr 2013
|
Louis Berger- USA - |
88
Salem-Ulundrupet (BOT-1/TN-06) km. 0.313 to km. 136.670 Tamil Nadu
BOT |
68 |
136.357 |
Jan 2008
|
Jan 2011
|
Reliance Energy Limited-
Indian- |
May 2013
|
Technital SPA- Italy - |
89
Kandla - Mundra Port(Approved Length 73 Km)
Gujarat
BOT |
8A |
71.4 |
Jan 2011
|
Jul 2013
|
Reliance Infra Projects Ltd.-
Indian- |
Jun 2014
|
Dorsch Gruppe- Indian - |