Projects Completed in Last 2-3 Months Status : 31st January 2010 |
| S. No | Stretch | NH | Length(Km) | Funded By | Start Date | When Complete | State |
NHDP Phase III |
|||||||
| 1 | Elevated Highway from Silk board junction to electronic city junction | 7 | 9.98 | BOT | Jul 2006 | Jan 2010 | Karnataka |
On Golden Quadrilateral |
|||||||
| 2 | Allahabad Bypass Contract-II km 158 km - km 198 |
2 | 38.987 | WB | Jun 2004 | Dec 2009 | Uttar Pradesh |
| 3 | Allahabad Bypass Contract-III km 198 km - km 242.708 |
2 | 44.708 | WB | Nov 2004 | Dec 2009 | Uttar Pradesh |
On North South & East West Corridor Phase II |
|||||||
| 4 | Thopurghat to Thumpipadi (NS-25/TN) Km.163.40 to Km. 180.00 |
7 | 16.6 | NHAI | May 2005 | Jan 2010 | Tamil Nadu |
| 5 | Hyderabad Bangalore section (NS-2/BOT/AP-5) Km 135.469 to Km 211 |
7 | 74.65 | Annuity | Sep 2006 | Nov 2009 | Andhra Pradesh |
| 6 | AP/Karnatka border- Nandi Hill crossing & Devenhalli to Meenu Kunte Village Km 463.6 to Km 527 & km 535- km 539 |
7 | 61.38 | Annuity | Mar 2007 | Dec 2009 | Karnataka |
| 7 | Kadal to Armur (NS-2/BOT/AP-8) Km 278 to Km 308 |
7 | 31 | Annuity | May 2007 | Nov 2009 | Andhra Pradesh |
| 8 | Gogunda to Udaipur (RJ-3) km.104 km to km 73 |
76 | 31 | NHAI | Jan 2006 | Dec 2009 | Rajasthan |
| 9 | Karur to Madurai (TN-4) Km 305.6 to Km 373.275 |
7 | 68.125 | BOT | Oct 2006 | Nov 2009 | Tamil Nadu |
Other Phase II Projects |
|||||||
| 10 | Tovaramkurchi to Madurai (Package -VII B) Km 60.95 to Km 124.84 |
45B | 63.89 | NHAI | Feb 2006 | Dec 2009 | Tamil Nadu |
|
|